John Guest - Warehouse steel

81 Apollo Drive, Albany.
Structural steel: 
A&S Engineering Ltd
Consulting engineer: 
MSC - Quiggy
Detailer: 
Sunrise Draughting Ltd

John Guest - Warehouse steel

Contractor: 
Haydn & Rollett
Client: 
Haydn & Rollett Developments No.1 Ltd
Construction value: 
1.7m
Duration: 
21 weeks (May 2013 to Oct 2013)
Scope of work and statistics: 
  • A 9 metre high warehouse structure incorporating 34 tons of steel and purlins
  • Steel to support the front office
  • Awnings at the office entrance and into the warehouse
  • Purlins with 19 metre spans (purlins supplied by Steel & Tube)
  • Portals 9 metres high x 23 metres wide
  • Steel to support concrete floor in office
  • Job to be completed in 6 weeks including 3D drawings and workshop drawings
  • We met the programme and had steel ready ahead of time with only 3 small defects over the entire project

A&S Engineering were engaged to carry out the Structural Steel subcontract for the John Guest Warehouse & Office Project, this package included Shop Drawings, Manufacture and Installation. The Upfront approach with the shop drawing process and coordination with other structural trades ensured the components fitted together without clashes.

Due to an extremely confined site there were a number of methodology issues to consider prior to starting on site, these items were all considered and the onsite erection process went smoothly and met or exceeded the programme requirements. Late in the project there was a design change that added an additional column, the design was issued on a Thursday and the Column was erected on the Saturday in an area where fit out had begun.

Working with Jim, Sue and the rest of the team at A&S was a pleasure, their performance on the project was superb.
 Sam McPhee — Site Engineer